Major construction at Church Avenue B & Q subway station kicks off August 5
PROSPECT PARK SOUTH — PLANNED SERVICE CHANGES to the Church Avenue B and Q line subway station will begin Monday, Aug. 5, and continue through early next year while crews make accessibility improvements, MTA said in a release Wednesday. The work was expected to begin in July but was delayed. Crews will install two new street-to-platform elevators, two new stairways, a new fare control area, ADA compliance upgrades to existing boarding areas, platform edges, sidewalks, stairways and agent booth upgrades.
Service changes include: Trains will run on the local tracks between the Prospect Park station and the Kings Highway station in both directions; through Fall 2024, southbound trains will bypass the Church Avenue station on the local track; and beginning Fall 2024 and continuing through the end of the year, northbound trains will bypass Church Avenue on the local track. Refer to https://new.mta.info/ for details.
✰✰✰